http://www.denys.be

GASUNIE - Wijngaarden-Westerschelde Oost

Construction of the 48” HP gas transport pipeline between Wijgaarden and Westerschelde Oost

The pipeline is located over a total length of ± 50 km in the “Buisleidingenstraat”. The construction comprises as well as different culvert syphons, open crossings, covering-overs :

- Construction in an existing tunnel ( 1.900 m)
- 8 HDD (5.400 m)
- 3 trenchless crossings of railways (240 m)
- 8 pipe jackings (851 m)
- 31 trenchless crossings (708 m)
- 7 AGI’s