STAD ANTWERPEN

KRUGERBRUG

Demolition of the old Krugerbug in Hoboken and construction of two new bicycle and pedestrian bridges, including all surrounding construction. The same project also includes 3 pipejackings under the railway, the construction of +- 560 m heat network DN400 and 150 m drinking water supply pipe DN400 commissioned by Fluvius and Water-link. Timing: from July 2021 to October 2022.